Underground lines, out of the way of Mother
Nature and human nature, do not experience many of the typical
problems of above-ground lines--like tree and limb falls,
car-pole conflicts, or ice and wind loading. Still, there is a
price to pay for those benefits
|
 |
1. Test trench layout for full-scale
field-testing is designed to confirm analytical predictions of
cable temperature. The extreme climatic and soil conditions in
Arizona provide ideal worst-case testing conditions
|
Underground distribution systems cost more than overhead systems
to install and replace. From an operational standpoint, the two
biggest challenges are knowing the actual load capability of an
underground line and taking care of aged and aging underground
cables.
Avoid heat-related
outages
Lack of actual in-service, thermal information about underground
cables was a key cause of several outages in the US during summer
1999, according to the US Dept of Energy's Power Outage Study Team
Final Report (POST), March 2000. Without real-time information,
engineers must rely on typical book ratings, which use simplified
assumptions regarding environmental conditions, mechanical and
electrical characteristics, and load-carrying capability. This
conventional thermal model is most useful when estimating the
temperature of single cables. Calculating the power flow and
temperature rise for combinations of conductors under varying types
of cover requires a much more sophisticated analysis.
Accurate knowledge of thermal conditions along a full cable route
helps identify hot spots, typically the limiting point in an
underground circuit. By using fiberoptic fiber, installed along the
length of the cable (or in a nearby spare duct), a utility can
periodically monitor the cable temperature and create temperature
profiles that enhance the information available from calculated
estimates or conventional fixed-point temperature sensors. Cable
temperature profiling using a fiberoptic line and computer software
is now available to utilities wanting to get a temperature profile
on underground cable runs. The profiling identifies the location of
hot spots--allowing cables to be rated to the hot spot. Further, new
underground transmission cables are now available from most major
cable manufacturers with fiber already in place for temperature
sensing.
The distributed fiberoptic (DFO) temperature sensing system is
owned by the Electric Power Research Institute, Palo Alto, Calif,
and licensed for use to Power Delivery Consultants (PDC), Ballston
Lake, NY. The temperature monitoring equipment used with the DFO
system is the DTS-80 from York Sensors Ltd, Chandlers Ford, England.
An enhanced optical time domain reflectometer (OTDR) injects a laser
pulse down a conventional communications type multimode fiber. The
OTDR detects the reflections and specialized software develops a
temperature profile accurate to within 1C, at roughly 3-ft intervals
along the length of the cable.
DFO system suitable for
all
 |
2. Both perpendicular and oblique
crossings were tested
|
Because the thermal environment of underground cables stays
relatively constant, only occasional DFO measurements are necessary
to identify hot spots. Once located, the hot spots can be
continuously monitored with a less expensive thermocouple and
data-logger.
Nevada Power Co (NPC), Las Vegas, Nev, recently used the DRO to
evaluate a new, 69-kV underground cable feed adjacent to the Aladdin
Hotel and Casino in Las Vegas.
The underground feeds consist of three 1500- and three 500-ft
runs of 2000-kcmil copper conductor, cross-linked polyethylene
(XLPE)-insulated, lead sheathed cable. Each cable includes two
single mode and two multimode embedded fibers in hollow steel tubes
wrapped around the cable just under the lead sheathing, placing the
sensing cable less than 1 in. from the copper conductor. The cables
are in a concrete-encased, 6-in. PVC duct bank.
Art Davoren, senior project manager, NPC, says, "The 69-kV system
was first tested without load to establish a baseline cable
temperature profile."
After being energized for 90 days, a second set of measurements
was taken, this time while under load. Davoren adds, "A thermocouple
was placed some 15-20 ft away from the duct bank at the same depth
to measure the earth's ambient temperature. Hourly loads were
recorded for 14 days immediately prior to the cable temperature
measurements in order to calculate line load and loss factors.
"We found short lengths (where the two cable runs came together
and a distribution circuit was about 5 ft away laterally) showing
temperatures higher than the design calculations. Earth
ambient--particularly under asphalt--is also somewhat higher. The
findings resulted in a slight derating of the cable," remarks
Davoren.
He cautions that the load readings were taken in December 2000, a
period of relatively light load on the NPC system. Additional
testing and analysis are planned for the peak load period expected
this summer.
San Diego Gas & Electric Co, San Diego, Calif, has also
identified and located hot spot bottlenecks on several distribution
feeders using the DFO technology. Book cable ratings based on
simplified assumptions about loading, cable characteristics, and
operating environment are generally conservative. In some cases,
additional load capacity (of critical importance as electric
utilities deal with the pressures of a competitive marketplace) is
available.
Southern California Edison Co (SCE), Rosemead, Calif, used the
DFO system to evaluate a scheduled reinforcement project for a 66-kV
transmission circuit over 8000 ft long. A temperature
characterization of the circuit determined that a 7-8% load increase
was possible without compromising safety or reliability. Based on
the results, SCE was able to defer the reinforcement project for
about two years.
URD not immune
The temperature issue is not limited to transmission cable.
Engineers have long made underground cable loading decisions based
largely on calculated estimates and past practices--with little
knowledge about the actual performance of cables in the ground.
Thanks to the efforts of the Distribution Systems Testing
Application and Research (DSTAR) group, utilities now know more.
DSTAR is a cooperative research effort supported by utilities and
utility organizations. The DSTAR Program Manager Reigh Walling,
General Electric Power Systems Consulting, Schenectady, NY, says,
"DSTAR projects are directed at solving problems that will improve
applied technology." Research focuses on day-to-day engineering and
operational issues--such as cable ampacity.
In situations where cables are in parallel for a short distance
or cross one another with a separation of more than a couple of
feet, the effects on cable ampacity are typically ignored.
Field tests, hosted by Arizona Public Service Co, Phoenix, Ariz,
and administered by PDC circulated 300-400 amp through 750 kcmil and
No. 1/0 cables both direct-buried and in duct (Fig 1). Testers tried
two configurations; short taps into a switchgear cabinet and
padmount transformer; and perpendicular and oblique crossings (Fig
2). Engineers also loaded a single reference cable to establish a
temperature baseline.
DSTAR found that a significant elevation of cable temperature can
occur at crossings of greater than 2-ft separation, and in
situations like parallel taps to padmount transformers where cables
are laid parallel for a short distance (Fig 3). Testing program
manager, John Cooper, PDC, comments, "Crossings could produce hot
spots on fully loaded cables as can differences in surface cover,
such as asphalt parking lots or roads."
As a result of the testing, engineers developed a method to
calculate cable temperature elevation and subsequent de-rating. The
software package called XDerate is available to DSTAR members for
use in underground system design.
Find fault
|
|
3. Situations where cables are paralleled
for a short distance, such as entry to and exit from
transformers and switchgear, were also tested
|
Once buried, some might be tempted to forget about underground
lines. They should think again. According the POST study,
underground distribution system cable failure was a factor in major
outages at Consolidated Edison Co of New York Inc, New York, NY,
July 1999; Public Service Electric & Gas Corp, Newark, NJ, July
1999; and Commonwealth Edison Co, Chicago, Ill, July 30-Aug 12,
1999. In each case the failure of individual distribution cables led
to a cascade of additional failures magnifying the impact of the
single original failure.
Indeed underground residential distribution (URD) cable
deterioration is perhaps the most onerous of problems with older
underground lines. As an inexpensive and better performing
alternative to paper-insulated lead covered (PILC) cable, mile upon
mile of high molecular weight polyethylene (HMWPE) cable was
installed by utilities across the US during the sixties and
seventies. Long before expected, failure rates for cables installed
prior to 1980 approached 20 failures per 100 miles of installed
cable. That is not reassuring, since an estimated 2-billion ft of
pre-1980 underground cable remains in service today.
Newer insulations--such as XLPE and ethyl propylene rubber (EPR)
were developed to resolve the reliability problems. Failure rates on
newer underground cables improved to about 1 failure per 100 miles
of cable. But, even with the newer insulations, problems with
treeing and neutral corrosion in aging, nonjacketed cable have not
gone away.
Cables in the ground, particularly the aged and aging URD cables
installed prior to 1980, are a problem waiting to happen. Visual
inspections are impossible and conventional direct current
high-potential testing may actually aggravate potential weak spots.
KEMA Diagnostic Services, Chalfont, Pa, uses very low frequency
partial discharge (VLF PD) technology on distribution cable systems
up to 35 kV to locate defects and give an indication of the risk of
failure. The VLF PD method discovers and measures the intensity of
partial discharges. The method involves sending a 0.1-Hz,
high-voltage pulse, 1.5 to 2.0 times the phase-to-ground voltage,
down the cable. A discharge diagram showing partial discharges as a
function of cable length is prepared and analyzed by a trained
operator to determine the significance of partial discharge to cable
health.
The test method is considered nondestructive and can handle
branched cable circuits and long cables using a multi-ended, global
positioning system (GPS). The branched circuit cable testing method
uses a GPS for time reference, a computer for data processing, a
communications unit to transfer data, and a master/slave unit to
control triggering of the remote terminals. The system identifies
potential failure points in the cable and accessories and gives
maintenance personnel a chance to target suspected problem areas.
Field-testing is also used by the Utilx Corp, Kent, Wash, to
determine the location of faults, splices and corroded neutral
wires. Recently, Keith Lanan, Utilx, developed a sub-nanosecond time
domain reflectometer (TDR) test method. Using a specially designed
impedance transition device (ITD), the TDR measures the amplitude of
a returning pulse to determine magnitude and location of splices and
neutral corrosion. The objective is to decide whether a cable is
suitable for rehabilitation. Based on Utilx statistics, not all
cable is worth that investment, but for the 60 to 90% that is, there
is a fix that will add about 20 years to cable life.
Fix the problem
The fix option (cable rehabilitation) has established an
impressive track record over the past several years. Older cables,
even those that have failed repeatedly, can be treated with
CableCure, a dielectric enhancement fluid, licensed and marketed
exclusively through Utilx. The CableCure process has eliminated
failures and prolonged service life on older cables worldwide.
Moisture in insulation voids and high-voltage stress contribute
to cable deterioration. The CableCure restoration treatment repairs
the damage by injecting a silicone fluid into stranded cable. The
fluid drives out the moisture and stops the deterioration. The
treatment cost is one-third to one-half that of replacement cost.
Actual life extension is with CableCure is estimated at 20 years.
CableCure fluid has successfully restored feeder and distribution
cables from 15 to 35 kV and transmission lines from 46 to 115 kV.
The process has proved particularly effective on URD systems with
direct-buried cable.
This widely accepted alternative to repairing or replacing bad
cable is being used at Salt River Project, Phoenix, Ariz, where a
project to treat some 600,000 ft of underground cable with
CableCure/XL is under way. According to Matt Crucitt, CableCure
project manager at Salt River, some 250,000 ft have already been
treated.
According to Carol Jaeger, senior engineer, Puget Sound Energy
(PSE), Bellevue, Wash, PSE has used CableCure injection on some 42
miles of underground lines. Jaeger comments that PSE is in the
process of identifying additional areas with stranded conductors and
bare concentric neutrals to determine which cables must be repaired
or replaced--rather than treated.
—Bill Koch
|